PennDOT ROAD WORK in MONROE COUNTY for the WEEK of 07/16/18

Traffic Restriction
Reporting unit:  Bridge (Inspection)
County:  Monroe
Municipality:  Stroud Township
Road name:  Gaunt Road (Over Interstate 80)
Between:  PA 33 And:  US 209
Type of work:  Inspection
Work being done by:  PennDOT Bridge Inspection Forces
Type of restriction:  Daytime
Restriction:  7/19/18  Interstate 80 Westbound Right Lane from 9am-12pm
7/19/18  Interstate 80 Westbound Left Lane from 12pm-3pm
Start date:  7/19/2018
Est completion date:  7/19/2018
Restrictions in effect (time of day):  9:00 AM To:  3:00 PM
Will rain cause delays?:  Yes
Change/Update:

Traffic Restriction
Reporting unit:  Maintenance
County:  Monroe
Municipality:  Barrett Township
Road name:  PA 447
Between:  Pike County Line And:  PA 390
Type of work:  Other
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction for spray patching. Please use caution driving through work zone.
Start date:  7/20/2018
Est completion date:  7/20/2018
Restrictions in effect (time of day):  9:00 AM To:  3:00 PM
Will rain cause delays?:  No
Change/Update:

Traffic Restriction
Reporting unit:  Maintenance
County:  Monroe
Municipality:  Stroud Township
Road name:  Interstate 80
Between:  Exit 305 (US 209 Bus) And:  Exit 302 (PA 611)
Type of work:  Other
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction westbound for bridge inspection. Expect delays and please use caution driving through work zone.
Start date:  7/19/2018
Est completion date:  7/19/2018
Restrictions in effect (time of day):  9:00 AM To:  3:00 PM
Will rain cause delays?:  Yes
Change/Update:

Traffic Restriction
Reporting unit:  Maintenance
County:  Monroe
Municipality:  Hamilton Township
Road name:  US 209
Between:  Interstate 80 And:  PA 33
Type of work:  Other
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction for spray patching. Please use caution driving through work zone.
Start date:  7/16/2018
Est completion date:  7/18/2018
Restrictions in effect (time of day):  9:00 AM To:  3:00 PM
Will rain cause delays?:  Yes
Change/Update:

Traffic Restriction
Reporting unit:  Maintenance
County:  Monroe
Municipality:  Middle Smithfield Township
Road name:  PA 402
Between:  Marshalls Creek And:  Pike County Line
Type of work:  Drainage
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction. Please use caution driving through work zone.
Start date:  7/16/2018
Est completion date:  7/20/2018
Restrictions in effect (time of day):  9:00 AM To:  3:00 PM
Will rain cause delays?:  Yes
Change/Update:

Traffic Restriction
Reporting unit:  Maintenance
County:  Monroe
Municipality:  Pocono Township
Road name:  Sullivan Trail
Between:  Crescent Lake Drive And:  Back Mountain Road
Type of work:  Drainage
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction for pipe replacement. Expect delays and please use caution driving through work zone.
Start date:  7/16/2018
Est completion date:  7/20/2018
Restrictions in effect (time of day):  9:00 AM To:  3:00 PM
Will rain cause delays?:  Yes
Change/Update:

Traffic Restriction
Reporting unit:  Construction
County:  Monroe
Municipality:  Delaware Water Gap Borough
Road name:  Interstate 80 at Exit 310 (Delaware Water Gap)
Between:  Exit 309 (US 209) And:  New Jersey State Line
Type of work:  Construction
Work being done by:  PennDOT Contractor
Type of restriction:  Nighttime
Restriction:  Interstate 80 will be closed and detoured for bridge beam setting. Eastbound will be closed and detoured Monday and Tuesday nights, westbound will be closed Wednesday and Thursday nights. The detour in both directions will utilize the on and off ramps at Exit 310. Please use caution and follow posted detour signs.
There will also be lane restriction in the eastbound directions of Wednesday and Thursday nights.
This work is related to the ongoing  Interstate 80 Exit 310 Project.
Start date:  7/16/2018
Est completion date:  7/20/2018
Restrictions in effect (time of day):  10:00 PM To:  5:00 AM
Will rain cause delays?:  No
Change/Update: