PennDOT ROAD WORK in NORTHAMPTON COUNTY for the WEEK of 10/01/18
County: Northampton
Municipality: Wilson Borough
Road name: US 22
Between: PA 33 and Bushkill Drive
Type of work: Inspection
Work being done by: PennDOT Bridge Inspection Forces
Type of restriction: Daytime
Restriction: Eastbound lane restriction.
Start date: 10/10/18
Est completion date: 10/10/18
Restrictions in effect (time of day): 09:00 AM To 01:00 PM
Will rain cause delays? Yes
Change/Update: RESCHEDULING THIS INSPECTION FROM 9/20 DUE TO WEATHER / RESTORATION EFFORTS BY COUNTY MAINTENANCE
County: Northampton
Municipality: Palmer Twp.
Road name: PA 248
Between: Butler Street and Northampton Street
Type of work: Inspection
Work being done by: PennDOT Bridge Inspection Forces
Type of restriction: Daytime
Restriction: Lane restriciton in both directions for bridge inspection.
Start date: 10/17/18
Est completion date: 10/17/18
Restrictions in effect (time of day): 09:00 AM To 03:00 PM
Will rain cause delays? Yes
Change/Update: THIS BRIDGE WILL BE INSPECTED ALONG WITH 48 0022 0200 0000 AS THEY ARE WITHIN 300 FEET OF EACH OTHER. NOTE: FLAGGING MAY BE NEEDED AT INTERSECTION
County: Northampton
Municipality: East Bangor
Road name: PA 512
Between: High Street and Broad Street
Type of work: Milling & Paving
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restricition with flagging.
Start date: 10/1/18
Est completion date: 10/5/18
Restrictions in effect (time of day): 09:00 AM To 02:00 PM
Will rain cause delays? Yes
Change/Update:
County: Northampton
Municipality: Williams Township
Road name: Hexenkoph Road
Between: Buttermilk Road and Raubsville Road
Type of work: Drainage
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 10/1/18
Est completion date: 10/3/18
Restrictions in effect (time of day): 09:00 AM To 02:00 PM
Will rain cause delays? Yes
Change/Update:
County: Northampton
Municipality: Williams
Road name: Cedarville Road
Between: Morgan Hill Road and South Delaware Drive
Type of work: Pothole Patching
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 10/4/18
Est completion date: 10/4/18
Restrictions in effect (time of day): 09:00 AM To 02:00 PM
Will rain cause delays? Yes
Change/Update:
County: Northampton
Municipality: Lower Saucon Township
Road name: Apple Butter Road
Between: Lower Saucon Road and Ringhoffer
Type of work: Bridge Repair
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 10/5/18
Est completion date: 10/5/18
Restrictions in effect (time of day): 09:00 AM To 02:00 PM
Will rain cause delays? Yes
Change/Update:
County: Northampton
Municipality: East Allen Township
Road name: Seemsville Road
Between: PA 329 and Old Carriage Road
Type of work: Pothole Patching
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 10/1/18
Est completion date: 10/3/18
Restrictions in effect (time of day): 09:00 AM To 02:00 PM
Will rain cause delays? Yes
Change/Update:
County: Northampton
Municipality: Lehigh Township
Road name: Walnut Drive
Between: Lehigh Drive and 21st Street
Type of work: Pothole Patching
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 10/4/18
Est completion date: 10/5/18
Restrictions in effect (time of day): 09:00 AM To 02:00 PM
Will rain cause delays? Yes
Change/Update:
County: Northampton
Municipality: Lehigh Township
Road name: Blue Mountain Drive
Between: Riverview Drive and County Line
Type of work: Shoulder Work/Widening
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 10/1/18
Est completion date: 10/5/18
Restrictions in effect (time of day): 09:00 AM To 02:00 PM
Will rain cause delays? Yes
Change/Update:
County: Northampton
Municipality: Pen Argyl
Road name: PA 512
Between: Woodward Avenue and Park Avenue
Type of work: Drainage
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: No restriction.
Start date: 10/1/18
Est completion date: 10/1/18
Restrictions in effect (time of day): 09:00 AM To 02:00 PM
Will rain cause delays? Yes
Change/Update:
County: Northampton
Municipality: Washington Township
Road name: Center Street
Between: Wall Street and Sunset Drive
Type of work: Drainage
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: No restriction.
Start date: 10/2/18
Est completion date: 10/5/18
Restrictions in effect (time of day): 09:00 AM To 02:00 PM
Will rain cause delays? Yes
Change/Update:
County: Northampton
Municipality: Lower Mount Bethel
Road name: Franklin Hill Road
Between: Uhler Road and PA 191
Type of work: Shoulder Work/Widening
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 10/1/18
Est completion date: 10/5/18
Restrictions in effect (time of day): 09:00 AM To 02:00 PM
Will rain cause delays? Yes
Change/Update:
County: Northampton
Municipality: Lower Nazareth Twp.
Road name: PA 248/Easton-Nazareth Highway
Between: Hollo Road and Jandy Blvd
Type of work: Bridge Repair
Work being done by: PennDOT Contractor
Type of restriction: Daytime
Restriction: Single lane conditions for bridge repair work. After that there will be a lane shifting at this location until November 11.
Start date: 10/1/18
Est completion date: 10/3/18
Restrictions in effect (time of day): 07:00 AM To 04:00 PM
Will rain cause delays? No
Change/Update:
County: Northampton
Municipality: Bethlehem
Road name: US 22
Between: PA 191 and PA 512
Type of work: Bridge Repair
Work being done by: PennDOT Contractor
Type of restriction: Nighttime
Restriction: Lane restriction in both directions for bridge maintenance work. This work i spart of the ongoing LVTS Bridge Maintenance Project.
Start date: 9/26/18
Est completion date: 11/12/18
Restrictions in effect (time of day): 09:00 PM To 06:00 AM
Will rain cause delays? No
Change/Update: